You cap at eight to ten homes a year so you and Jeff are on every job — and every "how's it looking?" text from a GTA owner still lands on one of your two phones. Here's a portal that answers it before it's asked: each owner logs in and watches their own home move through the stages, with the week's site photos, schedule, and open-book numbers already attached. Same crew, same attention — minus the interruptions. Sample build shown.

BUILD #MC-2612 · broke ground 06 May 2026

The Ridge House — custom 4-bed timber-frame chalet

Lot 12, Escarpment Ridge, Blue Mountains · owners in Toronto (Leaside)
Framing
Your Friday digest is ready — Week 11
Auto-compiled from this week's site photos, the schedule, and your cost tracker. Adam & Jeff review it; it sends itself Friday 4pm. Nobody had to stop building to write it.
Compiled 2026-07-17 · 07:00 · sent to 2 owners
Site & excavation06 May
Foundation02 Jun
Framingnow · 64%
4Envelope & roofest. Sep
5Mechanicalsest. Oct
6Interior finishest. Jan
7Handoverest. Mar '27

This week on site

photos + notes from the crew
Second-floor walls stood — framing 64% complete
Great-room ridge is up; you can finally read the escarpment views from the loft window openings. On schedule for roof trusses early Sept.
2026-07-16 · 15:40 EDT · added by Jeff
Main-floor deck & walls framed
Subfloor down, exterior walls sheathed and squared. Window rough-openings match the approved drawings.
2026-07-09 · 16:10 EDT
Foundation stripped & backfilled — passed inspection
Weeping tile and waterproofing in, backfill complete. Town framing inspection booked.
2026-06-02 · 11:20 EDT
Excavation & footings poured
Sited to the survey; footings poured and cured. Weather cost us two days — reflected in the schedule.
2026-05-14 · 09:05 EDT
Ground broke on the Ridge House
Welcome to the build. You'll get a photo update every Friday, and the numbers stay open-book the whole way.
2026-05-06 · 08:30 EDT

Build summary

Home4-bed timber chalet
StageFraming · 64%
Site superJeff Mighton
Project mgrAdam Mighton
Target handoverMar 2027

Open-book to date

cost-plus
Contract est.$1,540,000
Costs to date$612,400
Approved changes+$18,900
Vs. budgeton track

Documents

IMG Week 11 site photos View
PDF Approved drawings v3 View
PDF Change order CO-04 View
PDF July cost statement View

Next milestone

Framing → roof trussesstarts ~04 Sep
FRAMING 64%ENVELOPE & ROOF
Why this exists: the boutique model is the product — two owners on every one of ten builds. But at ten builds, the "just checking in" texts and the Friday photo round-up are a tax on the exact two people who should be on site. This portal compiles the week's photos, schedule, and open-book numbers itself and sends one clean update per home, every Friday. It protects the personal touch instead of replacing it — the owner still texts Jeff when it matters; they just stop having to text him to find out it's fine. Sample data shown — a real build wires to your job files and cost tracker.